In 2011 Epcotec delivered 6 engagements across Edmonton, Calgary, Banff, Jasper. Every engagement is recorded below - sector, work delivered and how it was achieved. No client names, by policy; references are available on request. The full 734-engagement register lives on one page here.

Epcotec starts in Edmonton. Six projects in the founding year, and the founding HFTRS method (lidar and photogrammetry fused in one pass, sub-5-millimetre point accuracy) goes straight to work on civil, transportation and municipal infrastructure surveys, including remote-sensing investigations in the Rocky Mountains parks. Digital from day one: every deliverable is a georeferenced dataset, not a drawing set.

2011 · 6 of 734 engagements recorded
01
Municipal · arterial network

Arterial corridor resurvey ahead of a capital works programme, acceptance per 100 m segment.

HFTRS fused lidar-photogrammetry; positional accuracy certificates per segment.

02
Municipal · arterial network

Continuation of the arterial resurvey across remaining corridors.

HFTRS one-pass acquisition; continuous accuracy certification pipeline.

03
Transportation contractor

First digital condition record for maintained roads, per-segment baseline.

IRI and rutting profiles fused with located imagery; normaliser with exception queue.

04
Transportation contractor

Condition baseline extension to the secondary network.

Mobile fused mapping; referencing crosswalk to the contractor network model.

05
National parks · Jasper

Access-corridor and terrain-hazard investigations inside Jasper National Park.

Terrestrial lidar with ground-return terrain modelling; ecological calendar scheduling.

Delivered by Epcotec Ltd, Vancouver

06
National parks · Banff

Corridor and infrastructure-footprint investigations inside Banff National Park.

Fused terrestrial acquisition; hazard and corridor registers without off-season intrusion.